Decide site. Select Turbine & Tower. Get specs. Shop for
best supplier. Obtain Building Permit. Place order.
START WORK.
|  Dig a hole
|
 Build foundation with anchor bolts and place in hole
|
 Pour concrete
|  Let it cure for a few weeks
|  Trench from tower site to electric meter pole
|  Lay cable
|  Con an old friend into stopping by and helping assemble, pull cable, and "test raise" tower-THANK YOU Janice & Dave!
|  "Test raise" successful
|
 Lower tower. Connect cable.
Attach turbine
|  Attach blades
|  Raise tower and turbine
|
 Secure base to anchor bolts
|  Just need final inspections and 2-way meter install
|  After inspections Michal throws the switch -
|
 - and Voltair is generating 11:53 am 11/4/08
|